Processing Plant – Improvement Hard Rock Tons per Hour / Tons per Day

January 6, 2022 | No related items found.

Related Services

Related Industry

Share This Article

Our client, one of the world’s leading mid-tier gold mining company.

Key Results 

40%

Potential Improvement Hard Rock Tons per Hour at Gyratory Crusher

Optimizing our Process Plant begins with managing the sizes of the ore at the different stages of the process. This begins with the larger size ore being delivered by Haul Trucks from the mine to the very fine particle size required to recover the gold from the ore.

At the initial stage, the opening of the Gyratory Crusher was reduced from 6.0 inches to 4.5 inches. The opening at the Secondary Crusher was reduced to 1.5 inches. The Apron Feeder, another component early in the process, has been rebuilt increasing a tested capacity from 1,200 to 1,700 tons per hour. The repair on the tunnel also now enables the speed increase of the Apron Feeder from 65% to 75%.

In addition to the increased process capacity, less energy is required which reduces our costs and helps the environment.
Also, a refurbished rock breaker is currently being installed to reduce downtime and increase throughput.

Elements

  1. Managing the “F80” / size of ore feeding into the Plant
  2. Managing the CV2 conveyor (Hard Rock) and CV3 conveyor (Soft Rock)
  3. Replaced the Head Pulley for less slippage and less lagging
  4. Potential now to process daily demand of ore in 12 hours using two 777s and one 993LU for improved blending
  5. Refurbished rock breaker now being installed

* We take client confidentiality seriously. While we have kept the brand anonymous, the results are real.

Further Reading

Operational Excellence

Case Studies

2025/10/21
Middle Eastern food and beverage company reduces expiry returns to 2.18%, unlocking US$839K in value

Operational Excellence

Case Studies

2025/10/16
How a global oil and gas company reduced maintenance backlogs by 30%

Operational Excellence

Case Studies

2025/10/16
24% OEE and 22% Productivity gains for Asian leading wood panel manufacturer

Operational Excellence

Posts

2025/10/10
How to Measure and Improve Shop Floor Productivity to Drive Manufacturing Growth

Digital Transformation

Case Studies

2025/10/10
Brazilian energy provider reduces manual workload by 16% after process automation 

Operational Excellence

Case Studies

2025/10/10
India’s Leading CDMO Overhauls Systems, Driving Operational Excellence

Operational Excellence

Case Studies

2025/10/09
Tractor Manufacturer Achieves 40% Increase in Average First Pass Yield

Operational Excellence

Case Studies

2025/10/09
Webbing Maker: 30% Waste Reduction. Better Quality Product